Central School Building Committee · Meeting of May 12, 2026

EAST BRIDGEWATER — The Central School Building Committee unanimously approved a $4.3 million construction management amendment during its May 12 meeting. The amendment brings the revised CM contract to $4,346,566, covering general conditions and site work. The committee also unanimously approved April project invoices of $762,187.55, all within budget.

Site work is underway with material importation and water control construction progressing; CD60 drawings are due June 2, and Massachusetts School Building Authority reconciliation is scheduled for June 23-26.

In the full story:

  • The complete report — 195 words

Source: the Central School Building Committee meeting of May 12, 2026, reported from the official video recording and transcript.

Keep reading with a 14-day free trial

Subscribe to East Bridgewater News to keep reading this post and get 14 days of free access to the full post archives.

Already have an account? Sign in. Ask about this instead

A subscription gets you:

  • Subscriber-only posts and full archive
  • Post comments and join the community
  • 24x7 access to local news

Subscribe to East Bridgewater News

Don’t miss out on the latest issues. Sign up now to get access to the library of members-only issues.
jamie@example.com
Subscribe